Magnetic Springs sewer project progressing

 

By Michael Williamson, Richwood Gazette

While the bid for the Magnetic Springs sanitary sewer system project may be slightly delayed, project leaders said it is still on track to be completed next year.

Local officials and community members met Tuesday to update residents on cost estimates, the latest timeline and how those living near the planned connector line will be affected.

Commissioner Dave Burke was in attendance Tuesday night and updated the Union County Commissioners Wednesday morning, saying the project is going “about as smoothly as possible.”

“It was overall very positive,” he said. “Lots of options and no immediate need for decisions until this summer. …

Read this entire article as it appeared in print in our eEdition

LATEST NEWS
Sharpening the tool set
Local Sports
In the photo on the left, North Union’s Gabby Lindsey takes a shot from beyond the arc during a scrimmage session against Riverdale. In the photo belo...
November 22, 2024
Snowplow artists
Local News
Students at North Union Elementary engaged in a “Design a Snowplow” challenge. Classes broke into small groups to come up with a design that would enc...
November 21, 2024