Richwood officials approved a contract for the new water treatment plant, an important first step in bringing the project forward.

At the regular village council meeting Monday evening, council voted to approve the tentative bid award contingent upon a successful approval of Ohio EPA loan financing.

The bid award went to Shinn Brothers Inc., a contractor out of Celina, for $4.6 million.

Craig Knapke, the project manager with Access Engineering, told council that the bid was the only one that came in and actually came in higher than the estimate.

“The bid was $4,670,000. It was over the estimate of $4,250,000 but wi…

Read this entire article as it appeared in print in our eEdition

LATEST NEWS
Wildcats awarded All-Ohio honors
Local Sports
By Bob Putman, Richwood Gazette Members of North Union’s football program received honors as the Ohio Prep Sports Media Association recently announced...
December 18, 2025
Community
The Richwood Civic Center would like to wish all of you a merry Christmas and happy new year. Our offices will be closed starting Dec. 24 and then ove...
December 18, 2025
Retiree honored
Community
During Monday’s meeting of the North Union Board of Education pictured at left, Superintendent Justin Ufferman, right, took time to recognize Brian Na...
December 18, 2025
Fire – EMS
Community
FIRE Dec. 7 5:04 a.m. – North High Street in Larue (house fire) Dec. 13 9:56 a.m. – Beatty Avenue (open burning) 2:39 p.m. – Route 31 (MVA) EMS Dec. 7...
December 18, 2025
NUMS provides year-end review
Local News
Administrative staff at the North Union Middle School (NUMS) gave statistics and first-hand accounts of growth in the school building to board of educ...
December 18, 2025